Eskom’s Majuba power station rail project debacle

The original business case for the 68km Majuba Rail Project was authorised in December 2004 with a board-approved cost to completion of R1.5 billion. This has since ballooned to an estimated R5.9 billion currently, plus R2.1 billion in capitalised interest during construction. The project is running many years late, and is now only expected to be completed by the end of March 2021.

Besides the above project capital cost overruns, the extended time overruns have incurred significant additional internal operating costs and external road repair costs (see below) that have further added to the devastating impact this project has had on Eskom, the built environment, and ultimately on the economy.

Nobody at Eskom appears particularly interested in quantifying these openly, perhaps because the realities are simply to ghastly to share publicly.

Background to the project

Eskom’s 4 110 megawatt (MW) Majuba coal-fired power station, situated near the towns of Amersfoort and Ermelo in the Gert Sibande District Municipality of Mpumalanga, comprises three 657MW dry air-cooled units and three 712MW water-cooled units. Construction on the power station started in September 1983, and by April 1996, 13 years later, only the first unit was connected to the grid. The last unit was commissioned in April 2001.

Fourteen million tons of coal per annum (14Mtpa) is required to fuel the power station, and this was supposed to come from a new tied-colliery built and operated by Rand Mines. However, development of the underground works stopped in 1993, and the mine was prematurely decommissioned when geological faults were belatedly discovered in the coal seam.

As a result of the decommissioning of Majuba Colliery, a branch rail link with a capacity of 8Mtpa was built from Palmford on the Natal Corridor (Natcor) general freight line between Standerton and Volksrust to Majuba Power Station. Due to a surplus of Eskom generation capacity at that time, the construction of Majuba was deliberately delayed, and at the end of the second quarter of 1996, only the first unit was in commercial operation.

The capacity of the Palmford rail link from the Natcor line was therefore more than adequate to meet the initial coal supply requirements of Majuba Power Station.

But from about 2003/2004, Eskom commenced a policy of procuring coal from new emerging sources, which resulted in delivery of coal by road even though the capacity of the Palmford line could still accommodate the volume of coal required. This was because the location of some of the new coal sources contracted to supply coal to Majuba made it impossible to move coal to Majuba via the Palmford line, and coal deliveries by rail were thus supplemented and displaced by delivery of coal by road.

The Majuba Coal Transportation System (CTS) Project

However, based on forecasts of electricity demand growth, Majuba Power Station had to gear up from a burn rate of 2.2Mtpa in early 2000 to a required capacity of 14Mtpa by 2010. The Palmford/Natcor line could not accommodate the increase in volumes, and in early 2000/2001 the need was identified to build a 68km rail line from Ermelo to Majuba, linking onto the heavy haul export rail line from Mpumalanga to Richards Bay.

The new line would have sufficient capacity to transport the full 14Mtpa of coal required by Majuba, which was to be offloaded at the Majuba terminal via an upgraded coal tippler system. This link would also shorten the distance that coal would have to be transported by rail from the Witbank coalfields, thus reducing rail coal supply costs by an estimated 15%. The original business case for this CTS project was approved by the Eskom board in December 2004 with a cost to completion of R1.5 billion.

Challenges in executing the project

However, significant “challenges” have been experienced by Eskom in executing the project.

These include delays in land acquisition for the rail servitude, funding constraints (which finally resulted in a R6 billion allocation in a $3.75 billion loan to Eskom by the World Bank in 2010), unforeseen underground conditions, adverse weather conditions, scope changes and disruptions by community pressure groups. The inquiry for the coal stockyard optimisation had to be issued three times due to unresponsiveness by the market. The works required for the interface with operational plant was delayed due to the need for power station outages. These outages were deferred several times due to issues with low coal stock levels at the power station. There were also problems with the signalling system contract and signalling equipment.

Finally, the main contractor went into business rescue and cancelled the contract with Eskom in July 2019, which led to subcontractors also leaving site.

Read: Aveng lodges R40m claim against Eskom

In December 2019, an incident occurred at the power station where the coal tippler takeout conveyor caught fire, and all coal deliveries by rail to Majuba since that date have ceased.

This means that since December 2019, the full coal supply requirements of Majuba Power Station have been met by road transport.

There have since been delays by National Treasury in the adjudication of a single-source contract – which is critical for the implementation of an expedited execution of the recovery works – and the completion of Majuba Rail Project, which is currently estimated by Eskom to be 87% complete.

On top of all this, Eskom has acknowledged that its own management of the project has been lacking. There have been several different project managers during the execution of the project, with varying qualifications and experience.

While Eskom has declined to name or discuss individual performance or names, it is in the public domain that poor project management is at the heart of a dispute between Eskom chief operating officer Jan Oberholzer and Mark Chettiar, the former general manager: coal and clean technology, and project manager for the Majuba Rail Project and the new ash dam project at Camden.

When confronted by Oberholzer about alleged underperformance in managing his project portfolio in September 2019, Chettiar informed the COO that he was taking “sick leave”, and has since been absent on full pay while he pursues the matter at the Commission for Conciliation, Mediation and Arbitration.

Additional internal operating costs and external road repair costs

When responding to specific questions on the impacts of fraud and under-delivery in the volumes and quality of coal to Majuba by road since 2003/2004, Eskom responded that there have been no such impacts arising from this.

However, various internal and external investigations and reports have indicated that since 2003/2004, the diversification of the coal supply within Eskom resulted in something of a free-for-all, where nepotism and fraud were apparent in the award of coal supply and transportation contracts to friends, family members and other politically connected persons.

Eskom has also indicated previously that the most frequent instances of coal supply fraud and coal quality breaches occur during the transport of coal by road by unscrupulous contractors to the various coal-fired power stations in South Africa, and that satellite monitoring and surveillance technologies have confirmed this.

Finally, the first tender process by Eskom since 2003/2004 for the transport of coal by road to Majuba Power Station was conducted in 2019, and the utility has since advised that this resulted in a 30% reduction in road transport costs to Eskom. From this, a good estimate of the massive operating losses suffered by Eskom at Majuba through excessive road transportation costs alone over the last 15 years can be made.

Furthermore, currently, at Majuba alone, Eskom is incurring additional costs of R62 million per year as a result of road transport, over and above what it would have paid for the transport of coal to Majuba using the old Palmford/Natcor rail link.

In addition, Eskom has indicated that had the new Majuba rail link been completed as planned, it could handle the full 14Mtpa coal requirements of Majuba, and would reduce the cost of coal to Majuba by 15% compared to that supplied via the old Palmford/Natcor rail link. Again, from this, a good estimate can be made of the massive operating losses suffered by Eskom over the last decade as a result of the many years of delay in the completion of the Majuba Rail Project.

Finally, there are the external costs of wear, tear and repair of local, provincial and national roads arising from the transport of coal by road to Majuba Power Station.

When asked about these road repair and resurfacing costs since 2003/2004, eyes glaze over and things become quiet and vague. It seems nobody at Eskom is prepared to venture a guess.

However, a competent firm of civil consulting engineers with road design experience could easily perform a study and provide a good estimate.

But there are now so many vested interests along the road transport supply chain, both within Eskom and in local communities and businesses, that nobody appears particularly interested in quantifying the cost of externalities outside of the direct cost to completion and capitalised interest during construction of the Majuba Rail Project. Perhaps the figures are too disturbing to the policy positions and project decisions already taken.

Eskom now acknowledges that even after the completion of the Majuba Rail Project, road transportation will continue for some time, and in fact, will probably never stop.

Conclusion

The policy started in 2003/2004 to truck coal to Majuba has spawned an entire ecosystem that feeds off the largesse of a state-owned enterprise that was out of control. A sense of entitlement has developed among parasitic elements – both within Eskom and externally – to extract as much they can, with little sense as to value for money and efficiency, to the wellbeing and sustainability of the host body, or to the national interest.

This also begs the question as to whether the extended project delays on the Majuba Rail Project may have been deliberately engineered by individuals, internal and external to Eskom, whose revenue streams – and those of their politically connected associates, friends and family members in the local coal mining and road transport businesses – would be negatively impacted by the timely completion of the project.

The fire incident in December 2019 that stopped all deliveries of coal by rail to Majuba Power Station is a particular case in point.

Source: moneyweb.co.za